Removal of 10kV power supply networks of HMMR production workshops
Implemented
2016
Directions - Electrical systems and networks.
Type of service - Design. Supply. Installation.
Industry - Industry.
DESCRIPTION
STAGES OF PROJECTS
DOCUMENTATION
PHOTO
Removal of 10kV power supply networks of HMMR production workshops
Scand Engineering Group (SEG) has completed a project to remove 10 kV electrical cable networks from a building site. The works were hampered by a short-term time period (36 hours), which was allocated for the production of works on the basis of the developed project of the production of works (CPD) and the schedule of work.
Also, the performance of work was hampered by difficult climatic conditions and snowfall.
STAGES OF PROJECTS
DOCUMENTATION
Removal of 10kV power supply networks of HMMR production workshops
PHOTOS FROM OBJECT