Scand Engineering Group (SEG) has completed a project to remove 10 kV electrical cable networks from a building site. The work was hampered by a short time period (36 hours), which ...
Development and maintenance of an outage (project of work) throughout the life of the project, taking into account Shutdowns. Development of the detailed design of the reconstruction
Mounted automation control technological equipment. The installation of cable trays with the laying of cable lines was carried out. Mounted and unplugged shields automation. Connected equipment and produced ...
Development and maintenance of PPR (project work) for the duration of the project. Development of the working draft. Supply of equipment for the implementation of ...